The following column is the Road Watch report for Okeechobee County for the week beginning Sunday, Aug. 10, provided by the Florida Department of Transportation.
Motorists are reminded to wear safety belts and drive with caution, courtesy, common sense, and patience as they travel through work zones. Remember, speeding fines are doubled in work zones.
SR 15 (US 441) from NW 20th Lane to NW 30th Lane: (Construction project) Crews will be performing curb ramp replacements and installing sidewalk, curb, and gutter at various locations along SR 15.
• Northbound and southbound single lane closures will occur throughout the project, with traffic being reduced to one lane as needed.
• Motorists should be aware of changing traffic patterns, heavy equipment, and workers present in the construction zone.
• Use caution when traveling through the area and obey posted signage and flagging operations. The estimated remaining duration of activities is 1 week
SR 15 (US 98/ US 441) from SE 30th Terrace to the Martin County Line: (Construction project) will begin resurfacing work on SR 15 (US 98) from SE 30th Terrace to the Martin County line in August 2025. The project includes pavement resurfacing, grinding, new pavement markings, and shoulder treatment.
• Starting Sunday August 10, 2025, nighttime lane closures will occur on SR 15 from NE 39th Blvd. to NW 3rd St. for milling and resurfacing operations. The closure is expected to last for 2 weeks.
• Motorists should be aware of changing traffic patterns, heavy equipment, and workers present in the construction zone.
Estimated project completion is early 2026.
SR 15 from NE 39th Blvd to NE 120th St: (Construction project) Crews are performing milling and resurfacing operations along this segment of SR 15.
• Work began on July 28, 2025, with daytime lane closures from 7 a.m. to 7:30 p.m. Northbound or southbound lanes will be reduced to one lane as needed.
• Crews will be performing milling and resurfacing operations only at nighttime from 7:30 p.m. to 6:00 a.m.
• Northbound and southbound single outside lane closures will take place, with traffic being reduced to one lane as needed and both lanes will not be closed simultaneously.
• Motorists should be aware of changing traffic patterns, heavy equipment, and workers present in the construction zone. Use caution when traveling through the area and obey posted signage.
Estimated remaining duration of activities: 4–5 weeks
Overall project completion is expected in summer 2026.
Districtwide Movable Bridges (Okeechobee County): (Construction Project) The Florida Department of Transportation is installing Intelligent Transportation Systems (ITS) at the US 41/US 98 (SR 700) Taylor Creek Bridge in Okeechobee County. This project includes the installation of pedestrian/bicycle detection systems, conduits and electrical components, and connection to bridge tender buildings.
• Bridge work is anticipated to take 3-4 weeks to complete construction.
• Motorists are advised that there will be intermittent sidewalk and lane closures throughout the duration of construction.
• Motorists should expect lane closures during the nighttime/overnight hours from 7 p.m. to 6 a.m.
• Motorists are advised to use caution in the construction zone.
Variable message signs will be in place to alert drivers that work is underway. Estimated completion of construction is in October 2025.
As a reminder, travelers can visit www.FL511.com or dial “511” from their phone to learn about traffic conditions on major roadways across the state.